Client: A&H Construction
Value: 4.75 million
We have recently completed 6 units in Lowry Park, Manchester for A&H Construction. Phase 1 on this project consisted off a 55,000 m3 Cut and Fill, Over 500m of Precast Retaining walls and associated groundworks for the 6 units with a total area of 16,000 m2.
Within the Extensive External Works Package there was over 10,000 m2 of Concrete Footpaths and Yards, 4000m of Kerbing and Edgings, Block Paved Footpaths and Various Roads and Car Parks to be prepped for Tarmacking.
Furthermore, there was 3000m of Drainage ranging from 100mm to 750mm and a 1750 m3 Attenuation Crated System.
Drumlisch worked Closely alongside A&H Construction to deliver this project on time in tough weather conditions and to achieve PC on the first opportunity. We look forward to further working with A&H as we move forward onto the Symmetry Park project in Liverpool.